ATTACHMENT B
<br />NOT -TO- EXCEED T&M FEE SCHEDULE
<br />CITY OF SAN MARCOS
<br />MCKIE AND LEE STREET WATER REPLACEMENT
<br />10 SEPTEMBER 2015
<br />Task
<br />Description
<br />Project
<br />Manager/
<br />Engineer
<br />185
<br />Weston Solutions, Inc.
<br />Graduate
<br />Engineer Engineer Senior CAD
<br />III IV / GIS
<br />J 130 a100 $112
<br />Admin.
<br />$73
<br />WESTON
<br />Subtotals
<br />Hrs Amt
<br />Topo Survey
<br />Byrn &
<br />Associates
<br />(Attachment B3)
<br />Geotechnical
<br />Investigation
<br />Holt
<br />Engineering
<br />(Attachment B2)
<br />Total
<br />1000
<br />'PRELIMINARY PHASE (30%)
<br />Project Meetings (1 Meeting)
<br />2
<br />2
<br />4
<br />$570
<br />$570
<br />Data Collection and Review
<br />4
<br />2
<br />6
<br />$546
<br />$546
<br />Site Visits
<br />4
<br />4
<br />$400
<br />$400
<br />Staff Meetings
<br />2
<br />2
<br />2
<br />2
<br />8
<br />$1,054
<br />$1,054
<br />Topographic Survey
<br />2
<br />4
<br />6
<br />$818
<br />$15,000
<br />$15,818
<br />Subsurface Utility Locate
<br />(Included in
<br />Supplemental Services)
<br />Geotechnical Investigation
<br />(Included in
<br />Supplemental Services)
<br />Environmental & Permitting Review
<br />2
<br />2
<br />12
<br />8
<br />24
<br />$2,726
<br />$2,726
<br />Archeological (THC Coordination Letter)
<br />4
<br />4
<br />$400
<br />$400
<br />Determine Alignment
<br />1
<br />8
<br />8
<br />17
<br />$1,881
<br />$1,881
<br />Identify Utility Providers
<br />1
<br />8
<br />1
<br />30
<br />$1,058
<br />$1,058
<br />Preliminary Opinion of Probable Construction Cost
<br />1
<br />2
<br />8
<br />1
<br />12
<br />$1,318
<br />$1,318
<br />Deliverable- Brief Tech Memo (3 Hard Copies, 1 PDF)
<br />1
<br />2
<br />8
<br />6
<br />17
<br />$1,683
<br />$1,683
<br />,Subtotals
<br />12
<br />8
<br />60
<br />22
<br />10
<br />112
<br />$12,454
<br />$15,000
<br />$0
<br />$27,454
<br />Subcontractor Markup (10%)
<br />$11500
<br />$0
<br />$1,500
<br />Allowance for Reimburseables (S %)
<br />$623
<br />$623
<br />PRELIMINARY PHASE 30% TOTAL
<br />13 077
<br />16 500
<br />0
<br />29 577
<br />2000
<br />DESIGN PHASE (60/90/100%)
<br />Project Meetings (2 Plan Rev. Meetings, @60% &
<br />4
<br />4
<br />8
<br />$1,140
<br />$1,140
<br />@90%)
<br />Public Meeting & Exhibits (1 Meeting)
<br />2
<br />4
<br />6
<br />$818
<br />$818
<br />Design Phase Site Visits
<br />4
<br />4
<br />$400
<br />$400
<br />Permitting Submittals
<br />2
<br />8
<br />2
<br />12
<br />$1,206
<br />$1,206
<br />SWPPP
<br />1
<br />1
<br />8
<br />12
<br />22
<br />$2,459
<br />$2,459
<br />60% Plans (4. 11 "'x17 " Sets + 1 PDF) (Cover Sheet,
<br />2'
<br />2
<br />12
<br />40
<br />4
<br />60
<br />$6,602
<br />$6,602
<br />Project Layout Sheet, Traffic Control Sheets, Tree &
<br />Erosion Sedimentation Control Sheets, List of Standard
<br />Details, and Special Details)
<br />60% List of Specifications
<br />1
<br />2
<br />12
<br />15
<br />$1,645
<br />$1,645
<br />60% Opinion of Probable Construction Cost (OPCC)
<br />1
<br />2
<br />4
<br />7
<br />$845
<br />$845
<br />60% Construction Schedule
<br />1
<br />2
<br />3
<br />$385
<br />$385
<br />90% Plans (4 - 11 "x17" Sets + 1 PDF) (Cover Sheet,
<br />4
<br />1
<br />8
<br />24
<br />4
<br />41
<br />$4,650
<br />$4,650
<br />Project Layout Sheet, Plan & Profile Sheets, Quantities
<br />By Sheet, Traffic Control Sheets, Tree & Erosion
<br />Sedimentation Control Sheets, Standard Details, and
<br />Special Details)
<br />90% Specifications
<br />1
<br />4
<br />8
<br />4
<br />17
<br />$1,797
<br />$1,797
<br />90% Opinion of Probable Construction Cost (OPCC)
<br />1
<br />2
<br />2
<br />5
<br />$645
<br />$645
<br />90% Construction Schedule
<br />1
<br />2
<br />3
<br />$385
<br />$385
<br />90% Bid Form
<br />1
<br />2
<br />2
<br />5
<br />$531
<br />$531
<br />99% Submittal (Unsealed Plans -4.11 "x17 " Sets +1
<br />1
<br />2
<br />4
<br />12
<br />1
<br />20
<br />$2,262
<br />$2,262
<br />PD
<br />100% Final Submittal ('Sealed Plans. 2 - 11 "x17" Sets + 1I
<br />2
<br />2
<br />16
<br />4
<br />1
<br />25
<br />$2,751
<br />$2,751
<br />PDF +1 CAD; Construction Checklist; Bid Form in
<br />MSWord; and Specifications in PDF)
<br />Subtotals
<br />23
<br />20
<br />96
<br />96
<br />18
<br />253
<br />$28,521
<br />$0
<br />$0
<br />$28,521
<br />Subcontractor Markup (10%)
<br />$0
<br />$0
<br />$0
<br />Allowance for Reimburseables (5 %)
<br />$1,426
<br />$1,426
<br />'DESIGN
<br />PHASE 90 300% TOTAL
<br />29 947
<br />0
<br />0
<br />29 947
<br />HM