<br />A. Contractor agrees to notify the Railroad Representative at least ten (10) working days in advance of Contractor
<br />commencing its work and at least ten (10) working days in advance of proposed performance of any work by Contractor in
<br />which any person or equipment will be within twenty-five (25) feet of any track, or will be near enough to any track that any
<br />equipment extension (such as, but not limited to, a crane boom) will reach to within twenty-five (25) feet of any track. No work
<br />of any kind shall be performed, and no person, equipment, machinery, tool(s}, material(s), vehicle(s), or thing(s} shall be
<br />located, operated, placed, or stored within twenty-five (25) feet of any of Railroad's track(s} at any time, for any reason, unless
<br />and until a Railroad flagman is provided to watch for trains. Upon receipt of such ten (10}-day notice, the Railroad
<br />Representative will determine and inform Contractor whether a flagman need be present and whether Contractor needs to
<br />implement any special protective or safety measures. If flagging or other special protective or safety measures are performed
<br />by Railroad, Railroad will bill Contractor for such expenses incurred by Railroad, unless Railroad and a federal. state or local
<br />governmental entity have agreed that Railroad is to bill such expenses to the federal, state or local governmental entity. If
<br />Railroad will be sending the bills to Contractor, Contractor shall pay such bills within thirty (30) days of Contractor's receipt of
<br />billing. If Railroad performs any flagging, or other special protective or safety measures are performed by Railroad, Contractor
<br />agrees that Contractor is not relieved of any of its responsibilities or liabilities set forth in this Agreement.
<br />
<br />B. The rate of pay per hour for each flagman will be the prevailing hourly rate in effect for an eight-hour day for
<br />the class of flagmen used during regularly assigned hours and overtime in accordance with Labor Agreements and Schedules
<br />in effect at the time the work is performed. In addition to the cost of such labor, a composite charge for vacation, holiday,
<br />health and welfare, supplemental sickness, Railroad Retirement and unemployment compensation, supplemental pension,
<br />Employees Liability and Property Damage and Administration will be included, computed on actual payroll. The composite
<br />large will be the prevailing composite charge in effect at the time the work is performed. One and one-half times the current
<br />urly rate is paid for overtime, Saturdays and Sundays, and two and one-half times current hourly rate for holidays. Wage
<br />tes are subject to change, at any time, by law or by agreement between Railroad and its employees, and may be retroactive
<br />as a result of negotiations or a ruling of an authorized governmental agency. Additional charges on labor are also subject to
<br />change. If the wage rate or additional charges are changed, Contractor (or the governmental entity, as applicable) shall pay
<br />on the basis of the new rates and charges.
<br />
<br />C. Reimbursement to Railroad will be required covering the full eight-hour day during which any flagman is
<br />furnished, unless the flagman can be assigned to other Railroad work during a portion of such day, in which event
<br />reimbursement will not be required for the portion of the day during which the flagman is engaged in other Railroad work.
<br />Reimbursement will also be required for any day not actually worked by the flagman following the flagman's assignment to work
<br />on the project for which Railroad is required to pay the flagman and which could not reasonably be avoided by Railroad by
<br />assignment of such flagman to other work, even though Contractor may not be working during such time. When it becomes
<br />necessary for Railroad to bulletin and assign an employee to a flagging position in compliance with union collective bargaining
<br />agreements, Contractor must provide Railroad a minimum of five (5) days notice prior to the cessation of the need for a
<br />flagman. If five (5) days notice of cessation is not given, Contractor will still be required to pay flagging charges for the five
<br />(5) day notice period required by union agreement to be given to the employee, even though flagging is not required for that
<br />period. An additional ten (10) days notice must then be given to Railroad if flagging services are needed again after such five
<br />day cessation notice has been given to Railroad.
<br />
<br />Section 2.
<br />
<br />LIMITATION AND SUBORDINATION OF RIGHTS GRANTED
<br />
<br />A. The foregoing grant of-right is subject and subordinate to the prior and continuing right and obligation of the
<br />Railroad to use and maintain its entire property including the right and power of Railroad to construct, maintain, repair, renew,
<br />use, operate, change, modify or relocate railroad tracks, roadways, signal, communication, fiber optics, or other wirelines,
<br />pipelines aM other facilities upon, along or across any or all parts of its property, all or any of which may be freely done at any
<br />Ie or times by Railroad without liability to Contractor or to any other party for compensation or damages.
<br />
<br />
<br />ibitA
<br />Page 1 of 4
<br />H:ldalaIWordltormslspeci'lllanguage IClfTT1SICROETexas.doc
<br />
|