Laserfiche WebLink
CITY OF SAN MARCOS <br />.` CHANGE ORDER <br />PROJECT: Comanche 24 -inch Water Transmission Main Project Date Prepared: 12/21/2012 <br />Change Order #: 4 <br />Santa Clara Construction, Ltd <br />9811 Anderson Mill Road <br />Austin, TX 78750 <br />We are submitting this Change Order to your contract. <br />This authorization provides for the following modifications or additions: Increase of quantities due to adjustments made in the field to accommodate conflicts during <br />construction as described in RFI 10, 12, 13, 16 and 19. In addition, several minor over -runs occurred due to typical construction conditions. Although the project does have <br />cost savings due to under -runs, a future change order is anctipated that will require the use of those funds. <br />1. <br />Bid Items Added <br />Days <br />Cumulative Sum <br />Cumulative % <br />Change <br />6/21/2012 ORIGINAL CONTRACT AMOUNT: ........................ <br />. ...... ... ..... $2,644,987.00 <br />ITEM NUMBER <br />ITEM SPEC REF. DESCRIPTION <br />QTY <br />UNIT <br />............................... $49,531.50 <br />UNIT PRICE <br />TOTAL <br />9 <br />5095 -1 Trench Safety <br />284.00 <br />LF <br />$ <br />1.00 <br />$284.00 <br />15 <br />SP510- AWRJ12 12" CL250 DIP Factory Restrained <br />85.00 <br />LF <br />$ <br />73.00 <br />$6,205.00 <br />16 <br />SP510- AWRJ16 16" CL250 DIP Factory Restrained <br />26.00 <br />LF <br />$ <br />99.00 <br />$2.574.00 <br />18 <br />SP510- AWRJ24 24" CL250 DIP Factory Restrained <br />116.00 <br />LF <br />$ <br />154.00 <br />$17,864.00 <br />25 <br />SP510 -KW DI Fittings <br />0.50 <br />TON <br />$ <br />30,000.00 <br />$15,000.00 <br />30 <br />SP511 S -Al2 12" Gate Valve <br />2'00 <br />EA <br />$ <br />3,000.00 <br />$6,000.00 <br />31 <br />SP511 S -A16 16" Gate Valve <br />2.00 <br />EA <br />$ <br />7,000.00 <br />$14,000.00 <br />187.00 <br />LF <br />$ <br />3.00 <br />$561.00 <br />59 <br />6425 Silt Fence <br />69 <br />510 1" Service Saddle <br />1.00 <br />EA <br />$ <br />500.00 <br />$500.00 <br />75 <br />SP510 -PR -D Pvmnt Repair 2" HMAC TY D <br />42220 <br />SY <br />$ <br />28.25 <br />$11,927.15 <br />76 <br />SP510 -PR -F Pvmnt Repair 4" Flex Base <br />423.00 <br />SY <br />$ <br />19.00 <br />$8,037.00 <br />90 <br />340S Pavement Repair Hmac TY A <br />55.00 <br />Ton <br />$ <br />134.38 <br />$7.390.90 <br />TOTAL CHANGE ORDER <br />$90,343.05 <br />ICHANGE IN DAYS REQUESTED FOR CHANGE ORDER <br />0 <br />Date Contract Document <br />Amount <br />Days <br />Cumulative Sum <br />Cumulative % <br />Change <br />6/21/2012 ORIGINAL CONTRACT AMOUNT: ........................ <br />. ...... ... ..... $2,644,987.00 <br />456 <br />$2,644,987.00 <br />00% <br />9/7/2012 CHANGE ORDER 1 :........................................................ <br />............................... $49,531.50 <br />0 <br />$2,694,518.50 <br />1.9% <br />9/20/2012 CHANGE ORDER 2: _ ....................................................... <br />............................. $16,682.36 <br />0 <br />$2,711,200.86 <br />2.5% <br />11/7/2012 CHANGE ORDER 3: ....................................................................................... <br />$45,000.00 <br />0 <br />$2,756,200.86 <br />4.2% <br />12/21/2012 CHANGE ORDER 4:... ..................................................................... <br />.............. $90,343.05 <br />0 <br />$2,846,543.91 <br />7.6% <br />REVISED CONTRACT AMOUNT: ...................................................................... <br />$2,846,543.91 <br />456 <br />Your signature below will constitute your acceptance of this Change Order <br />Prepar d By: / Contractor Appro I <br />12/21/12 <br />Shaun Condor, P.E., Project Engineer Date Tim Unger, Proj IZ7 ager Date <br />Revie d By Ap ove y: <br />z AD�k <br />Jaim chez, Inspections Manager ames R. Nuse, P.E., City Manager <br />Reco me anned By: <br />Linda Grub s Huf , .E., Director of ate <br />-3 <br />Engineering /Capital Improvements <br />