the scope change proposal upon Tyler's receipt of an approved scope change proposal during the <br />Response Period, subject to the availability of Tyler personnel unless otherwise mutually agreed. Tyler <br />acknowledges that any scope change proposal that affects the total cost of the project is subject to the <br />City's policies and that the Response Period must provide adequate time for City's consideration. City <br />acknowledges that such scope change proposals may affect the implementation schedule and Go -Live <br />Dates, which will be changed by mutual agreement. All scope change proposals shall be governed by the <br />terms and conditions of the Master Agreement, including the daily rates for services, unless mutually <br />agreed in writing otherwise. <br />CITY OF SAN MARCOS, TX PAGE 19 OF 62 <br />ERP PROJECT- FINAL SOW <br />