ATTACHMENT A <br /> CITY OF SAN MARCOS <br /> SESSOM DRIVE WASTEWATER REPLACEMENT FROM N. LBJ TO CANYON ROAD <br /> SCOPE OF SERVICES <br /> Project Understanding <br /> The work to be performed by Kimley-Horn and Associates, Inc. (KIM LEY-HORN or the Consultant) under <br /> this contract will consist of providing Design Phase (60%, 90%, 99%, 100% Documents), Bid and <br /> Construction Phase Services for the Sessom Drive Wastewater Replacement from N. LBJ to Canyon <br /> Road. The project consists of the following improvements: <br /> • Sessom Drive Sanitary Sewer—the replacement of up to approximately 1,800 linear feet of 12- <br /> inch sanitary sewer line from N. LBJ Drive to Canyon Road along Sessom Drive. <br /> • Canyon Road Water Line Relocation —the lowering of up to 60 linear feet of 12- and 12-inch <br /> water lines currently exposed within Sessom Creek. <br /> • Sessom Creek Bank Stabilization Project: Project Survey and Coordination—The Sessom Creek <br /> Bank Stabilization Project will be designed by John Gleason, LLC in a separate contract with the <br /> City. However, Kimley-Horn will provide topographic survey as described in Item 3.a of this <br /> scope. Kimley-Horn will coordinate with John Gleason, LLC during design to evaluate potential <br /> impacts of each project to the other. It is understood that: <br /> o Both the Sessom Drive Wastewater Replacement from N. LBJ to Canyon Road Project <br /> and the Sessom Creek Bank Stabilization Project will be combined and bid under one <br /> contract. <br /> o Kimley-Horn will be the lead engineer administering the contract on behalf of the City <br /> during bidding and construction. <br /> Basic Scope of Services <br /> Design Phase (60/90/99/100%) <br /> 1. Project Management and QA/QC: This task consists of effort associated with project administration, <br /> coordination with City staff, coordination and supervision of the project team, coordination with <br /> other projects specifically the Sessom Creek Bank Stabilization Project, and quality management <br /> so that project milestones and deliverables meet schedule and budget constraints. <br /> 2. Meetings <br /> a. Project Coordination Meetings: Two (2) utility coordination meeting have been budgeted <br /> for the Design Phase. It is assumed that meetings will be held prior to beginning 60% <br /> and 90% design. Kimley-Horn will attend meetings with City of San Marcos Staff and <br /> John Gleason, LLC Staff to determine project constraints and needs as well as discuss <br /> design considerations. <br /> b. Project Meetings: Three (3) project meetings have been budgeted for the Design Phase, <br /> following each milestone submittal (60/90/100%). <br /> c. Public Meetings: One (1) public meeting has been budgeted which consists of preparing <br /> exhibits and attending the meeting. <br /> 3. Tasks <br /> a. Topographic and Tree Survey: KIMLEY-HORN will prepare topographic and tree survey <br /> for the red boundary area, as shown in the attached exhibit (Exhibit A) provided by the <br /> 1 <br />