Docusign Envelope ID: BB4FCDA1-A564-4C7D-B116-E72FBD797168 <br />8.5 Proiect Review and Prioritization <br />The CONSULTANT will use the project ranking system and tool updated in Task <br />8.4 to evaluate the resulting list of projects identified in Task 8.3. It is envisioned <br />that the ranking system will sort projects based on high priority/short-term, <br />medium, or low priority/long-term ranking. The result of this task will be a project <br />map and table of results including planning level costs. <br />Deliverables: Prioritization Tool, Prioritized Map and List of Projects <br />8.6 Funding and Implementation <br />Eligibility of projects for funding via local, state, MPO, and federal resources will <br />be evaluated in this subtask, including identified safety projects from Task 3.6. <br />Identified opportunities for funding federal, state, regional, local, and other funding <br />sources will be identified and documented in presentation of a prioritized project <br />list in the Short -Term Capital Plan in Task 9.1. <br />Deliverables: Funding and Implementation Plan <br />9. PLAN REFINEMENT <br />9.1 Short -Term Capital Improvement Plan <br />The CONSULTANT will prepare planning -level cost projections for City -selected <br />future capital improvement projects based on 2027 dollars, likely to be the highest- <br />ranking projects identified in Task 8.5. These cost projections will be based on <br />discussion with City staff, current City design guidelines, recently bid roadway and <br />intersection projects in the City, and previous CONSULTANT experience with <br />roadway construction costs. Due to the variety of unknowns associated with <br />roadway project cost projections (ROW acquisition, utility relocations, etc.), the <br />planning -level project cost projections used in this analysis should be further <br />refined prior to being used for any future capital improvement planning within the <br />City. The CONSULTANT will develop costs for projects estimated to be in the <br />Short -Term (10 years or less) Capital Improvement Plan (CIP), which are <br />anticipated to be high and medium priority projects identified in Task 8.5. The CIP <br />list will be used to inform the Rough Proportionality Assessment, Task 7. <br />Deliverables: Planning Level Cost Sheets <br />9.2 Supportive Policies <br />The CONSULTANT will develop recommendations for new or updated policies <br />based on the resulting diagnostic table from Task 3.1 for further development by <br />the City. These policies will be identified in the TMP but not resolved or developed <br />for full implementation. <br />Deliverables: List of Recommended Policy Changes <br />City of San Marcos Kimley-Horn and Associates, Inc. <br />TMP Exhibit B Scope of Services Page 20 August 21, 2025 <br />