<br /> 2. Paragraph 3, Co~ensation to Engineer, as shown in the original <br /> agreeemnt, shall be modified as set forth herein. <br /> Delete paragraph 3.a. and add new paragraph 3.a. as follows: <br /> a. Step I Preliminary Engineering and Planning: The Engineer <br /> shall be compensated a lump sum of One Hundred Seven Thousand, <br /> Eighty Eight Dollars ($107,088) for the services described <br /> in Section 2.a.(1) through 2.a.(5) above. The Engineer shall <br /> in addition be compensated for professional services in con- <br /> nection with the Sewer System Evaluation Survey described in <br /> item 2.a.(6) above as shown in the following schedule. This <br /> schedule is based upon lump sum and unit cost items for esti- <br /> mated quantities. If services or quantities other than those <br /> described herein are required, they will be considered as <br /> "additional services" and the Engineer shall receive additional <br /> compensation. The manner of computing the compensation will be <br /> determined at the time the Engineer is authorized to proceed <br /> with said additional services. <br /> Schedule of Compensation <br /> 1. Mobilization (lump sum) $ 18,346.00 <br /> 2. Above Ground Physical Inspection <br /> 353,000 L.F. @ $0.108/L.F. $ 37,446.00 <br /> 3. Flow ¡.1onitoring <br /> a. Install/Remove <br /> $545/1ocation x 7 locations $ 3,815.00 <br /> b. Monitoring & Maintenance <br /> $385/day x 45 days $ 17,325.00 <br /> 4. Groundwater Gauges <br /> Installation - 5 locations x $449/1ocation $ 2,245.00 <br /> 5. Rain Gauges <br /> Installation - 45 days x $30/day $ 1,350.00 <br /> 6. Smoke Testing <br /> 353,000 L.F. x $0.14/L.F. $ 49,420.00 <br /> 7. Flow Isolation and Below Ground <br /> Physical Inspection <br /> $4l.20/manhole x 500 manholes $ 20,600.00 <br /> 8. Jet Cleaning <br /> 30,000 L.F. x $0.67/L.F. $ 20,100.00 <br /> 9. Internal Inspection <br /> 30,000 L.F. x $0.85/L.F. $ 25,800.00 <br />