Project Schedule <br />1.1.17 The following High -Level Timeline/Schedule includes: <br />Installation of Software — Total 5 days <br />a. Installation & Configuration at SWTP — 2 days <br />b. Installation & Configuration at WWTP — 2 days <br />2. Design and Build Screens — Total 40 days <br />a. <br />SWTP Tag Development - 3 days <br />b. <br />WWTP Tag Development — 9 days <br />c. <br />SWTP Tag Screen Development — 15 days <br />d. <br />WWTP Tag Screen Development — 28 days <br />e. <br />SWTP Reporting Design & Testing — 5 days <br />f. <br />WWTP Reporting Design & Testing — 5 days <br />g. <br />DFS HyperTACII (API) Integration — 10 days <br />3. Design Alarms & Thresholds — Total 7 days <br />a. SWTP Alarms & Thresholds — 2 days <br />b. WWTP Alarms & Thresholds — 5 days <br />4. Convert Lookout Historical Data — Total 10 days <br />a. SWTP Data Export — 2 days <br />b. WWTP Data Export — 2 days <br />c. Develop- script to insert data into new database — 5 days <br />Training — Total 25 days <br />a. System Documentation — SWTP — 5 days <br />b. System Documentation — WWTP — 5 days <br />c. SWTP End User Training - 4 days <br />d. WWTP End User Training — 4 days <br />e. SWTP Administrative Training — 2 days <br />f. WWTP Administrative Training — 2 days <br />g. IT Department Training —1 day <br />Database Connectivity <br />The Contractor will : <br />1.1.18 Enable Ignition to connect to a redundant physical server onsite at both locations <br />using credentials provided by the City. During operation, if connectivity or a problem with <br />the primary server renders it inoperative, then the secondary server with the database will <br />fail over and start working immediately. If both servers are down, because of a catastrophic <br />event, the Consultant will bring up a virtual server from a remote location and reroute the <br />City's access to the server, until the primary is operational and running. The City is <br />responsible for the permission and access to the database, and will provide the Contractor <br />with the appropriate rights to install, configure, and troubleshoot, remotely. The Contractor <br />