201 CONTRACT TO THE CITY OF SAN MARCOS - QT- 2901/3 <br />Attachment D <br />Change Control Management Agreement <br />This Change Management Control Agreement is part of the entire Agreement between the parties. Either parry <br />(the `Initiating Party') may initiate changes to the referenced Statement of Work by submitting a Change <br />Control Form to the other party (the `Receiving Party') as described in this Agreement. <br />Using the Change Control Form, the Receiving Parry will review any change requests, research all solutions, <br />conduct an impact analysis, propose alternative approaches, if any, and advise the Initiating Party of the <br />findings including any associated additional fees and schedule impacts within fourteen (14)calendar days of <br />the Receiving Party's receipt of any such Change Control Form. The Change Control Form will be provided to <br />the Customer by New Dawn. <br />Changes will be made as amendments to the Statement of Work and will set out the nature of the change, the <br />new fee and schedule, and any other agreed upon services. Amendments will only be effective when signed by <br />the Customer and New Dawn pursuant to: <br />1. Change Initiation <br />The Change Initiation step will be used to begin the process. An initiated Change Request Form may be <br />submitted by a Customer representative. The originator will deliver the form to the New Dawn Project <br />Manager for log entry. The completeness of the information provided will be checked, and will be assigned <br />a unique number to the change request. <br />2. Change Validation <br />The Change Validation step is performed by the individual designated by the New Dawn Project Manager. <br />The evaluation will be completed as either a change request (significant enough to impact cost, schedule, <br />or resources) or be placed on the project issue log. If the item is placed on the project issue log, the <br />evaluator selects the impact level (1= major, no work around identified, 2= major, with work around, <br />3= minor) and the source of the defect (baseline source code, Customer data, or Customer specific code). <br />3. Initial Impact Analysis <br />The Initial Impact Analysis step is performed by the individual designated by the New Dawn Project <br />Manager. The following are outlined: Affected Requirements, Proposed Alternatives, Impact on Cost, <br />Impact on Schedule, Impact on Resources, and Estimated Cost of Detailed Impact Analysis. <br />4. Initial Review Results and Approvals <br />The Initial Review Results step will be completed by the Customer Project Manager and the New Dawn <br />Project Manager. Agreement will be reached for one of four optional next steps: <br />a) If the initial impact analysis is of sufficient detail, the change will be approved and forwarded to the <br />New Dawn Project Manager for implementation. <br />O vL New Dawn <br />